| Month | Heavy Rain Days | Work-Stopping Cold | Heavy Snow Days | Workable % | Risk Level |
|---|---|---|---|---|---|
| April | 2 days | 0 days | 1 days | 73% | Low |
| May | 2 days | 0 days | 0 days | 87% | Low |
| June | 2 days | 0 days | 0 days | 87% | Low |
| July | 3 days | 0 days | 0 days | 77% | Low |
| August | 2 days | 0 days | 0 days | 81% | Low |
| September | 2 days | 0 days | 0 days | 87% | Low |
| October | 1 days | 0 days | 2 days | 65% | Medium |
| November | 1 days | 2 days | 3 days | 47% | High |
| December | 0 days | 5 days | 4 days | 29% | High |
| January | 0 days | 6 days | 5 days | 26% | High |
| February | 0 days | 4 days | 4 days | 46% | High |
| March | 1 days | 1 days | 4 days | 58% | Medium |
Work-Stopping Cold = days ≤0°F requiring full work stoppage. Days between 0°F and 25°F are workable with cold-weather methods (heated enclosures, accelerators, hot-water mix).
Total work-stopping days per month (Heavy Rain + Extreme Cold + Heavy Snow)
Historical averages only: Based on 10 years of past weather patterns. These indicate statistically favorable periods but do NOT predict specific conditions. Always monitor short-term forecasts.
Weather risk breakdown by construction phase — activity-specific thresholds applied per work type
The Lakewood Commerce Center project (Denver, CO · Apr 14, 2026 – Apr 13, 2027) presents Moderate overall weather risk with a composite score of 38/100. Of 365 project days, 257 (70.4%) are workable and 198 (54.2%) meet ideal construction conditions — well above the industry average for a Colorado mountain-adjacent location.
Primary risk: The exterior envelope phase (Oct 12–Dec 10) falls squarely across Denver's most volatile weather transition window. Temperature is the dominant risk factor, with 62% of nights in November historically dropping below 25°F — stopping sealant and roofing work. This phase has only 48% workability and is the critical path item requiring immediate contingency planning.
Opportunities: The foundation phase (May 30–Jul 28) lands in Denver's optimal 60-day window with 88% workability and zero freeze risk. Morning-scheduling crane operations during the steel phase captures an estimated 8–10 additional work days per month by avoiding afternoon lightning. The interior MEP phase is largely weather-immune at 91% workability.
Recommended action: Add 15–18 days of schedule float to Phase 4, accelerate Phase 3 completion by 2 weeks if possible, and pre-order all long-lead MEP materials before December 1. A 4.4-week weather contingency is statistically justified for this location and project duration.
Enter any location, any dates, any project type. Get this exact analysis for your real job site.